On October 20, 2026, a power fault in Google Cloud's europe-west2-b zone in London interrupted Revolut's payments and app across seven countries. Hyperscalers spend billions on redundancy and can still be taken down by a power event. A small facility cannot outspend that problem — but it can refuse the cheapest single points of failure, starting with the core switch.

One core switch is a decision, not a default

A MikroTik CRS518 — with 2×100G and 16×25G ports — lists at $1,595. A pair running MLAG costs a little over $3,000. Weigh that against one core failure: Uptime Institute's 2026 outage analysis attributes 23% of IT-service-related outages to network and connectivity issues, and 52% of major outages cost between $100,000 and $1 million each. At those numbers, a second core switch is not an upgrade. It is insurance with a very small premium.

Stacking is not redundancy

Stacked switches present as one logical device, which is exactly the problem: they share a control plane, so a stack-master failure or a stack-link fault shakes the whole unit. MLAG keeps two independent control planes that synchronize state — one box can lose power entirely and the other keeps forwarding, with no reconvergence event your customers can feel. If redundancy is written into your SLA, MLAG is the version you can defend.

Do the oversubscription math before you buy

An access switch with 48×1G ports can offer at most 48 Gbps. At a 3:1 oversubscription ratio, the design point is 16 Gbps of uplink — in practice, 2×10G LACP provides 20 Gbps (2.4:1) with sensible headroom. Under-provision the uplinks and the evening peak saturates them while customers complain; over-provision and you have paid for ports that will never light up. The ratio is the decision. The hardware follows from it.

Review power and network on the same sheet

The London incident was a power fault, not a network fault — but the network is always what customers notice first. A redundancy review that covers only switches misses the point: dual utility feeds, UPS runtime, and generator test results belong on the same one-page checklist as core redundancy.